Pump Replacement Project

Project Title

Municipal

Client

NI Water

CASE STUDY

Pump Replacement Project

About Mullaghanagh NI Water

Our team of experts at DPS are specialists when it comes to installation and maintenance of domestic sewage treatment plants.

Northern Ireland Water operate Mullaghanagh Point Water Treatment Works required 2 new 600mm nominal bore x 8mm wall mild steel pump shroud fabrications to replace their previous old system.

Our Team of experts removed the previous system as shown in the pictures on the next page, pressure washed the area and installed the new pipe and pumps to allow Mullaghanagh NI Water to have a more productive and efficient system to meet their output needs.

DPS & KSB

- A Powerful Combination -

As distributors of pumping and treatment products to the water, wastewater, agriculture and industrial sectors, DPS has been a supply partner to many companies for over thirty years.

Our supply agreements with global-best-in-class manufacturers allow us to offer premium level pumping, blended with mixing excellence and cutting-edge macerators with full factory backup.

Our pricing structure allows us to offer a full supply, installation and service solution for complete project delivery at no commercial disadvantage to you, our customer, for total confidence and seamless support.

DPS & KSB

- A Powerful Combination -

As distributors of pumping and treatment products to the water, wastewater, agriculture and industrial sectors, DPS has been a supply partner to many companies for over thirty years.

Our supply agreements with global-best-in-class manufacturers allow us to offer premium level pumping, blended with mixing excellence and cutting-edge macerators with full factory backup.

Our pricing structure allows us to offer a full supply, installation and service solution for complete project delivery at no commercial disadvantage to you, our customer, for total confidence and seamless support.

Industry Expertise

Project Scope

  • Removal of existing equipment within chamber.

  • Jet washing and cleaning of chamber.

  • Mechanical installation of new equipment

  • New Suction Valves DN150

  • New Discharge Pipework within chamber DN150

  • New Pressure Gauges and Stop valves

  • Two 600mm nominal bore x 8mm wall mild steel pump shroud fabrication with lidc/w DWI regulation 31 approved fusion bonded epoxy

  • Two UPA 250C-250/3l UMA 200D 55/21 50kW 400/3/50 10m cable c/w PT100 Temp sensors and 10m cable.

Design

Industry leading knowledge to help aid with the deisgn processes through a highly qualified and industry award winning team

Relationships

  • Supplier relationships of industry products

  • Industry relationships through years of experience and commercial success

  • Bringing contractors together to make the project run smoothly

MCC

  • Factory testing provided by R&R

  • After installation on site and power connected, the MCC will be tested again

Training Plan

DPS will provide sufficient training to personnel to enable them to correctly and safely operate and after installation on site and power connected, the MCC will be tested