Feb 2017
COMPLETION DATE
€ 1
Project Value
During 2016, DPS had been requested by a leading international consultant engineering company to assist in the design of 2 separate pumping applications; 1 canister pump system and 1 large scale submersible pump system. Throughout the year we assisted the engineering company in the design, working very closely with them in relation to flow design, head calculations and specifically chamber design. This is an area where the client had limited knowledge, but the Technical Sales Team excelled.
We guided the client through all aspects of the project from design to commissioning.
DPS supplied 2 No. KSB KRTD 150-253/114UEG-S Pumps c/w pedestals and 11kW IE3 Motors and 2 No. Amacan K 800-401/506UG 48kW Axial Flow Pumps c/w DN800 Galvanised Mild Steel Canisters (Designed & Manufactured in-house by our Contracts Department).
DPS was not responsible for the installation of the pumping equipment on site, however, in order to ensure that the client met KSB’s exacting standards, we advised the M&E contractor on site in relation to the installation of the canisters, the installation of the pumps and the commissioning of the units. Careful consideration was given to the choice of hydraulic at this site as the requirements are very precise – when the pumps are needed to perform –they must. We ultimately chose the KSB “D – Screw Impeller” for the low flow submersible pump application (as it can deal will all types of solids and fibrous matter). Since commissioning, these pumps have been in operation without any issues
Having progressed from working with the design team to the supply and installation phase, DPS nominated a Project Manager who was the point of contact for both the M&E Contractor and the Consulting Engineer and he was responsible for all communications from DPS to both parties and the project stakeholders.
The Project Manager was responsible for Progress reporting to allow ‘live’ updating of the program schedule
Having progressed from working with the design team to the supply and installation phase, DPS nominated a Project Manager who was the point of contact for both the M&E Contractor and the Consulting Engineer and he was responsible for all communications from DPS to both parties and the project stakeholders.
The Project Manager was responsible for Progress reporting to allow ‘live’ updating of the program schedule
Having installed and commissioned the equipment on site as per the OEM/DPS’ requirements and in conjunction with the project stake holders, DPS then ‘snagged’ the site prior to handover to ensure there were no minor issues outstanding.
Once the snagging process was complete, the client was able to sign off and close-out the project.
Cookie | Duration | Description |
---|---|---|
cookielawinfo-checkbox-analytics | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookie is used to store the user consent for the cookies in the category "Analytics". |
cookielawinfo-checkbox-functional | 11 months | The cookie is set by GDPR cookie consent to record the user consent for the cookies in the category "Functional". |
cookielawinfo-checkbox-necessary | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookies is used to store the user consent for the cookies in the category "Necessary". |
cookielawinfo-checkbox-others | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookie is used to store the user consent for the cookies in the category "Other. |
cookielawinfo-checkbox-performance | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookie is used to store the user consent for the cookies in the category "Performance". |
viewed_cookie_policy | 11 months | The cookie is set by the GDPR Cookie Consent plugin and is used to store whether or not user has consented to the use of cookies. It does not store any personal data. |