Irish Water Dublin City Council
CLIENT
€ 1
Project Value
To supply specialist dust filters for a treatment process that we supply progressive cavity pumps.
Lime powder added to water for treatment causes dust that needs to be captured by filters before going into the air.
The customer could not go direct to the manufacturer because they were not on the customer’s approved supplier list.
A quite common occurrence for Irish customers supplied with products or equipment from foreign manufacturers/OEM’s.
They came to DPS because we are an approved vendor and have built a good relationship with the customer over the years, based on technical expertise, trust and willingness to go the extra mile.
DPS contacted the foreign manufacturer and ensured all information of the equipment was correct, as well as, providing drawings and a sample to the customer. All was accomplished within a speedy time-frame.
Once the customer confirmed they were satisfied with the product and price submitted by DPS an order was immediately placed and dispatched.
The customer was so satisfied with the product and the ability of DPS to source and competitively price this non-core products they have subsequently requested and accepted offers for other non-core products such as filters for liquids, gear boxes, motors and valves.
DPS contacted the foreign manufacturer and ensured all information of the equipment was correct, as well as, providing drawings and a sample to the customer. All was accomplished within a speedy time-frame.
Once the customer confirmed they were satisfied with the product and price submitted by DPS an order was immediately placed and dispatched.
The customer was so satisfied with the product and the ability of DPS to source and competitively price this non-core products they have subsequently requested and accepted offers for other non-core products such as filters for liquids, gear boxes, motors and valves.
Having installed and commissioned the equipment on site as per the OEM requirements and in conjunction with the project stakeholders, DPS then ‘snagged’ the site to handover to ensure there were no minor issues outstanding.
Once the snagging process was complete the final sign-off and close-out of the project was completed in a timely manner and with ultimate client satisfaction.
Cookie | Duration | Description |
---|---|---|
cookielawinfo-checkbox-analytics | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookie is used to store the user consent for the cookies in the category "Analytics". |
cookielawinfo-checkbox-functional | 11 months | The cookie is set by GDPR cookie consent to record the user consent for the cookies in the category "Functional". |
cookielawinfo-checkbox-necessary | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookies is used to store the user consent for the cookies in the category "Necessary". |
cookielawinfo-checkbox-others | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookie is used to store the user consent for the cookies in the category "Other. |
cookielawinfo-checkbox-performance | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookie is used to store the user consent for the cookies in the category "Performance". |
viewed_cookie_policy | 11 months | The cookie is set by the GDPR Cookie Consent plugin and is used to store whether or not user has consented to the use of cookies. It does not store any personal data. |